If you manage a shopping strip, run a school's facilities budget, or are pricing civil works on a new build, you've probably noticed something frustrating. Ask three asphalt contractors for a price on the same car park and you can get three numbers that look like they're for three different jobs. One is per square metre, one is per tonne, and one is a lump sum with a page of exclusions.
This guide is for commercial work only. Driveways are a different job with different maths. Here we cover car parks, access roads, loading areas and school yards around Melbourne: what actually drives the commercial asphalt cost, and how to line up quotes so you're comparing like with like.
Any blog that gives you a single asphalt cost per square metre for commercial work is guessing. The rate on a 4,000 m² resheet of a warehouse car park in Dandenong South has almost nothing in common with a 300 m² patch of school yard in Brunswick where the trucks can't get through the gate.
What we can do is show you the six things that move the price, then walk through a real-world style comparison so you can check your own quotes.
Every asphalt job carries costs that don't care how big it is. A paver, rollers, a crew, a tipper or two, possibly a profiler (milling machine), plus getting all of that to site and back. Spread that over 3,000 m² and it barely registers. Spread it over 250 m² and it can be a big chunk of the square metre rate.
This is why a small commercial job often prices higher per square metre than a large one, and why bundling works makes sense. If your school has a car park, a bus bay and a few failed patches near the canteen, quote them together. One mobilisation beats three.
Asphalt is bought by the tonne. Going from 30 mm to 50 mm compacted thickness means roughly two thirds more material on the same area. That's not a small difference on a big site.
Thickness should follow what the pavement has to carry. A staff car park with light vehicles is a very different load to the corner where the bin truck swings around every Tuesday, or a bus loop outside a school gate. Turning heavy vehicles is where car parks tend to fail first. For anything with regular trucks or buses, ask for the pavement depth to be justified, not just picked.
Mix type matters too. In Victoria, the Department of Transport and Planning's Section 407 specification sets out the dense graded asphalt types, with Type N described as a light to medium duty Size 7, 10 or 14 wearing course for light to moderately trafficked pavements, and Type H as a heavy duty mix for moderate to heavily trafficked pavements. Councils often call up these specs directly. Wyndham City Council, for example, publishes Section 407 as part of its technical specifications. If your quotes name different mix types, they're not the same job.
The asphalt you see is the cheap part to estimate. The base underneath is where nasty surprises live.
If the existing pavement has cracked in a crocodile skin pattern, is pumping water, or has deep ruts, laying fresh asphalt over the top is just painting over the problem. It'll look great for one Melbourne winter and then the cracks will come back through. Those areas need digging out and rebuilding, and nobody knows exactly how much until the old surface is lifted.
Older school grounds and commercial sites can also turn up old fill, tree roots, or material that needs testing before it can be disposed of. That cost almost never appears in a first quote.
The fix is not to hope for the best. Ask every contractor for a schedule of rates for base repairs (per m² or per m³ at a stated depth) and a provisional quantity. That way the unknown has a price on it before work starts, instead of a variation you get handed on day two.
A tipper with hot mix needs room to back up to the paver. Narrow laneways, low carport roofs, tight gates, overhead power lines and soft ground all slow the job down. Slow means more labour hours and asphalt cooling in the truck.
Timing is part of access. A retail car park that has to stay open usually means staging the work in sections, sometimes at night or on weekends. Each stage can mean another mobilisation and penalty rates for the crew. Schools mostly avoid this by booking in holidays, but so does every other school. If you want the January break, lock it in by spring.
Even inside a private car park, you need a plan to keep people and vehicles away from the plant and hot asphalt. On a school site, that planning gets serious. The Victorian Department of Education's contractor rules require contractors to sign into and out of the site and complete all required paperwork before starting. Facilities managers often ask about Working with Children Checks. The Department's position is that a WWCC is not mandatory for all contractors working at schools, and depends on the nature of the work and the contact the contractor will have with children. Your school council can set a stricter rule, so check your local policy before you award the job.
If any part of the work touches the public road, nature strip, footpath or crossover, it's a different level of cost and paperwork. Under the Road Management Act 2004, you must obtain consent from the coordinating road authority before starting works and notify it once they're done, and councils such as Casey state that you will need a Traffic Management Plan for works within the road reserve, which includes the nature strip, footpath, kerb, channel and roadway. That can mean a traffic plan designer, permit fees, and qualified traffic controllers on the day. Ask each contractor who arranges the permit and whether traffic control is included or excluded. It's one of the most common gaps between quotes.
A car park isn't finished when the roller leaves. Bays, arrows, pedestrian crossings, hatching, wheel stops, signage and accessible parking all cost money. Accessible bays and their shared areas need to be set out to AS/NZS 2890.6, and getting that wrong can mean redoing it after a complaint or a certifier's inspection.
Some contractors include line marking. Many subcontract it and leave it out of the headline price. If one quote includes a full linemark layout and another doesn't, the cheaper quote may not be cheaper at all.
Two other items worth checking: drainage (pits, levels and falls, because asphalt over a puddle is still a puddle) and kerbing or edge restraint.
This is where most people get caught. A per-tonne price often looks cheaper because it usually covers only the asphalt laid. A per-square-metre price is more often an all-in rate for a defined scope. You have to convert them to the same basis.
The conversion is simple:
Tonnes = area (m²) x compacted thickness (m) x density (t/m³)
Dense graded asphalt compacts to roughly 2.3 to 2.45 tonnes per cubic metre depending on the mix. Using 2.4 is a fair working figure, but ask each contractor what density they've used.
So at 40 mm, each square metre takes about 0.096 tonnes. To turn a per-tonne rate into a per-square-metre rate for the asphalt alone:
Rate per m² = rate per tonne x thickness (m) x 2.4
The numbers below are illustrative. They're chosen to make the maths clear, not to serve as a price list.
1,500 m² staff car park. Mill off the old surface and lay 40 mm of Size 10 dense graded asphalt. Required tonnage: 1,500 x 0.04 x 2.4 = 144 tonnes.
$38 per m² all in, covering milling, disposal, tack coat and 40 mm asphalt. Total $57,000.
$330 per tonne supplied and laid, estimated 144 tonnes. Total $47,520. That's $31.68 per m², and it looks about $9,500 cheaper.
Now read Quote B's exclusions. Milling at $6 per m² is $9,000. Tack coat at $1.50 per m² is $2,250. Profiler float to site is $2,500. The real total is $61,270, or $40.85 per m². Quote B is now dearer.
Then there's tonnage risk. Quote B charges on actual tonnes laid. If the old surface is uneven and the average compacted thickness comes in at 45 mm instead of 40, that's 162 tonnes. Asphalt alone jumps to $53,460 and the total to $67,210. That's nearly 18 percent more than Quote A.
Per-tonne pricing isn't wrong. On irregular sites it can be the fairest method for both sides. But you need to know the estimated tonnes, the trigger for going over, and what's excluded.
Here's a protection most clients never use. Every load of asphalt leaves the plant with a weighbridge docket. Ask for copies.
Divide total tonnes by (area x 2.4) and you get the average thickness actually laid. If your 1,500 m² job was quoted at 40 mm and the dockets total 120 tonnes, the average is about 33 mm. On a per-m² contract, you paid for 40. It's a two-minute calculation and it keeps everyone honest.
Sometimes. If the existing pavement is sound and levels and drainage allow it, an overlay can be good value. If it's badly cracked or the levels already sit hard against door thresholds and kerbs, milling first is usually the right call.
Different loads, thicker or heavier duty mixes, compliance paperwork, traffic management, larger plant, and line marking. They're different products.
Possibly. Australia imports most of its bitumen, and its price follows global oil markets. Many commercial asphalt contracts include a rise and fall clause tied to bitumen. Major suppliers have flagged this openly, with Fulton Hogan noting in a price notice that the standard escalation relating to bitumen costs will continue to apply. Ask whether your quote is fixed and for how long.
Light vehicles can usually go on the same day once it cools, but avoid parking heavy vehicles or turning wheels on the spot during the first hot days. Line marking timing should be agreed up front.
Commercial quotes are often ex GST. Check before comparing.
Before you compare prices, send every contractor the same scope sheet: area, thickness, mix type, milling or not, base repair rates and provisional quantity, drainage, kerbing, line marking layout, traffic management and permits, working hours, and GST. Then ask each quote to state the tonnes assumed, density used, exclusions, rise and fall terms, and validity period. Request weighbridge dockets as a condition of payment.
Do that and the "cheapest" quote often changes. More importantly, you'll avoid the most expensive outcome of all, which is the car park that has to be dug up again in three years.
If you'd like a site measure and an itemised quote for a car park, access road or school yard anywhere in Melbourne, get in touch with MR Asphalt. We'll price it so you can compare it line by line.
Get in touchGOOD Based on 11 reviews Posted on Philippa SommerTrustindex verifies that the original source of the review is Google. Mike and his team did an excellent job on my driveway. Trouble free and smooth transaction. Fast reliable and friendly crew. Very professional and l’m very pleased.Posted on Annie StuartTrustindex verifies that the original source of the review is Google. Cannot praise MR Asphalt enough! Our new driveway is just gorgeous and the whole process from start to finish has been fantastic. Mike's prompt response to our enquiry followed by next day site check by Fraser, whole-team professionalism, courtesy, great communication, amazing workmanship and Kev's meticulous brick art has given us one of the best trade experiences of all time. More than highly recommended as this team is a total stand-out. Thanks again MR and we'll be in touch re our next job soon.Posted on Bronwyn LaphamTrustindex verifies that the original source of the review is Google. I could not be happier with the work of Fraser and Kev. They were polite, friendly, extremely professional and highly skilled with great attention to detail. Excellent communication throughout the process and they delivered as promised. I can't recommend them highly enough.Posted on brendan hamiltonTrustindex verifies that the original source of the review is Google. 10/10, couldn’t recommend enough! Fraser was great to deal with, friendly and the quality of work was top notch I couldn’t have found a better company to do my driveway Thanks Fraser and the guys from Mike Rowley AsphaltPosted on Danny KahTrustindex verifies that the original source of the review is Google. Great job, communicated which days they would be in to take out the old concrete, prepare crushed rock,do the brick edging, and final asphalt. Very happy with the result !!Posted on Harry BastinTrustindex verifies that the original source of the review is Google. Top blokes got everything done on time. Dealt with Fraser, easy process. Really happy with the driveway thanks guys.Posted on Sue CarlinTrustindex verifies that the original source of the review is Google. Great job. Mike and his guys were quick and efficient. Result looks amazing. Reasonably priced and very helpful.Posted on Emily GuyTrustindex verifies that the original source of the review is Google. Excellent work, great attention to detail. My driveway is looking schmick thanks to Mick!