The crew packs up, the new asphalt is jet black and smooth, and the driveway looks better than it has in fifteen years. Then the first proper summer storm rolls through. You open the roller door the next morning and there's a tide line across the garage floor, the cardboard boxes along the back wall are soggy, and the Esky is sitting in a puddle.
Nothing is wrong with the asphalt itself. The problem is height. The new layer went down on top of the old one, and nobody checked where that left the surface against the garage slab, the gutter and everything else it meets. If you're searching "asphalt overlay driveway too high", that's almost certainly what happened.
An overlay is a new layer of asphalt laid over the existing surface. For a residential driveway that layer is commonly in the 30 to 40mm range once it's rolled and compacted. Across the open middle of the driveway, an extra 35mm makes no difference at all.
The trouble is at the edges. Your driveway meets things that don't move: the garage slab, the kerb and gutter, the letterbox, the front path, pit lids, garden edging. When the driveway was first built, it was set to meet those at the right height. Add 35mm on top and every one of those junctions is now out by 35mm.
The usual shortcut is "feathering", where the new asphalt is tapered down to nothing at the edge so it meets the old level. It looks fine on day one. The catch is that asphalt needs a minimum thickness to hold together. A rule of thumb used across asphalt specifications is a layer at least two and a half to three times the size of the largest stone in the mix. Feather it thinner than that and the stones have nothing to grip. Those edges start to crumble and ravel, often within a couple of years, and usually right where your car turns.
This is the junction that costs money when it goes wrong.
The National Construction Code sets minimum heights for a slab above the ground around it. Under the deemed-to-satisfy provisions builders commonly work to, a slab on ground should sit at least 150mm above finished ground level, 100mm above sandy, well-drained areas, or 50mm above sealed areas like a driveway, provided that surface falls at least 50mm over the first metre away from the building.
Look at that last figure. Many garage entries were built close to that 50mm minimum. A 35mm overlay can wipe out most of the margin, and if the overlay also flattens out the fall near the door, water no longer runs away from the garage. It sits at the door, or it runs in.
There's a second issue almost nobody mentions: termites. Where the slab edge is part of the termite management system, there needs to be at least 75mm of exposed slab edge above the finished external level so termites can be spotted. Asphalt laid up against or over that edge hides the inspection zone. A building and pest inspector will often flag it when you sell.
Then there's the door. A roller door's bottom rail or a sectional door's seal is designed to close onto the slab. If the asphalt outside is now level with or above the slab at the door line, water ponds against the seal, and the seal can catch or wear on the new edge.
A quick check before any work: lay a straight piece of timber or a spirit level from the garage slab out over the driveway for one metre. Measure the drop. If it's already close to 50mm or less, an overlay without milling at the garage is asking for trouble.
The section between your front boundary and the road (the crossover or vehicle crossing) is usually on council land, and its levels are typically set by council. Many councils require a permit before anyone works on it. Check with yours, because some will make you rip out non-compliant work at your cost.
Overlaying right to the gutter leaves a raised lip at the edge of the road. That lip can hold water in the gutter instead of letting it run along, it creates a bump that low cars scrape on, and the thin edge breaks up under the weight of tyres turning in and out. The proper fix is milling a strip at the gutter end so the new asphalt meets the existing level flush. Contractors call this a tie-in or butt joint.
Australia Post asks that a single letterbox aperture sits between 0.9m and 1.2m above the ground. Honestly, a 35mm overlay rarely pushes a letterbox out of that range unless it was already sitting low, but a tape measure takes ten seconds.
The bigger letterbox problem is asphalt packed up against a brick pier or post footing. Water now sits against the base instead of draining past it. The same goes for meter boxes, sewer inspection openings, stormwater grates and pit lids in or beside the driveway. Each one either needs raising or needs the asphalt milled down around it. Each one is also a line item, and a quote that doesn't mention them hasn't looked properly.
Milling means grinding off the top layer of the old asphalt before laying the new one. You don't always need to mill the whole driveway. In plenty of cases, edge milling is the smart middle ground: a strip roughly one to two metres wide is milled down at the garage, the gutter and around fixed items, to the same depth as the new layer. The open middle is simply overlaid. You keep the cost of an overlay and get the levels of a full replacement where it counts.
Mill first, at least at the edges, when any of these apply:
You've got 50mm or less of step down from the garage slab, or the fall away from the door is flat.
The driveway has been overlaid before. Layers stack, and each one raises the levels again.
The driveway meets several fixed things such as kerb, garage, path and pits.
The old surface has rutting or soft spots. An overlay copies the shape underneath, so the problem comes straight back. Milling also exposes base failures that need repair before new asphalt goes down.
A straight overlay with no milling can be fine when there's a generous step down at the garage, the driveway edges run onto lawn or garden, and it doesn't meet a council gutter.
We're not going to throw out a per square metre figure for milling, because it swings a lot depending on access, the size of the job, where you live, and what happens to the millings. Any number that ignores those would be a guess. What we can tell you is what should appear on an honest quote:
Small driveway jobs are often done with a skid steer fitted with a milling attachment. Transport is a fixed cost, which is why it hits small jobs harder per square metre.
Old asphalt is often recycled, which can reduce disposal costs, but it still needs carting.
Ask for these as separate lines. Then weigh the extra against the alternative. Water damage to a garage, a re-do of failed edges in two years, or a council notice will cost more than milling a couple of strips.
Usually, yes. The high strip at the garage can be saw cut, milled out and relaid at the right level. Another option is a grated trench drain across the garage door. That only works if the drain connects to an approved stormwater point, and in most states connecting to stormwater is a job for a licensed plumber. A rubber threshold strip on the garage floor is a stopgap, not a fix.
Under the Australian Consumer Law, services must be provided with due care and skill. Setting levels is part of laying a driveway. Put your concern to the contractor in writing with photos and measurements first. If that goes nowhere, your state's fair trading or consumer affairs office is the next step.
Then you need the other owners' or the body corporate's agreement before work starts, and that includes agreement on levels at each garage.
No. A sealer coat is a thin film and doesn't change your levels in any meaningful way.
Spend fifteen minutes with a tape measure and a spirit level. Measure the step down at the garage, the fall over the first metre, the height at the gutter and the letterbox aperture. Take photos with the tape in shot. Then ask every contractor quoting the job one simple question: "What will the finished levels be at the garage, the gutter and the letterbox, and are you milling to get there?"
A contractor who answers that clearly has thought about your driveway. One who says "she'll be right, we'll feather it in" hasn't.
GOOD Based on 11 reviews Posted on Philippa SommerTrustindex verifies that the original source of the review is Google. Mike and his team did an excellent job on my driveway. Trouble free and smooth transaction. Fast reliable and friendly crew. Very professional and l’m very pleased.Posted on Annie StuartTrustindex verifies that the original source of the review is Google. Cannot praise MR Asphalt enough! Our new driveway is just gorgeous and the whole process from start to finish has been fantastic. Mike's prompt response to our enquiry followed by next day site check by Fraser, whole-team professionalism, courtesy, great communication, amazing workmanship and Kev's meticulous brick art has given us one of the best trade experiences of all time. More than highly recommended as this team is a total stand-out. Thanks again MR and we'll be in touch re our next job soon.Posted on Bronwyn LaphamTrustindex verifies that the original source of the review is Google. I could not be happier with the work of Fraser and Kev. They were polite, friendly, extremely professional and highly skilled with great attention to detail. Excellent communication throughout the process and they delivered as promised. I can't recommend them highly enough.Posted on brendan hamiltonTrustindex verifies that the original source of the review is Google. 10/10, couldn’t recommend enough! Fraser was great to deal with, friendly and the quality of work was top notch I couldn’t have found a better company to do my driveway Thanks Fraser and the guys from Mike Rowley AsphaltPosted on Danny KahTrustindex verifies that the original source of the review is Google. Great job, communicated which days they would be in to take out the old concrete, prepare crushed rock,do the brick edging, and final asphalt. Very happy with the result !!Posted on Harry BastinTrustindex verifies that the original source of the review is Google. Top blokes got everything done on time. Dealt with Fraser, easy process. Really happy with the driveway thanks guys.Posted on Sue CarlinTrustindex verifies that the original source of the review is Google. Great job. Mike and his guys were quick and efficient. Result looks amazing. Reasonably priced and very helpful.Posted on Emily GuyTrustindex verifies that the original source of the review is Google. Excellent work, great attention to detail. My driveway is looking schmick thanks to Mick!