On paper, the summer break hands you six weeks of empty school grounds. In practice, if you are planning schoolyard resurfacing over the 2026/27 holidays, you have closer to three weeks of usable site time, and about ten to fifteen productive days once weather is factored in.
That gap between what the calendar says and what a crew can actually do is where most of the pain comes from. Not the asphalt. The calendar.
This is a scheduling guide, written for business managers, principals and council facilities officers who have to make the dates work, sign the contract and then explain to 600 families why the basketball courts are fenced off in week two of Term 1.
Term 4 2026 finishes on different days depending on where you are:
Now start subtracting.
Christmas Day falls on Friday 25 December 2026. Boxing Day is the Saturday, which triggers a substitute public holiday on Monday 28 December. New Year's Day is Friday 1 January 2027. That alone eats the back half of December.
If you are in NSW and need anything signed, approved or paid by the department, the government sector Christmas closedown for 2026/27 runs from 25 December 2026 through to 8 January 2027. A variation that lands on someone's desk on 22 December is not getting looked at until the second week of January.
Then there is the one nobody puts in a brochure. Most asphalt plants and civil crews in Australia shut down from around 18 or 19 December and come back the first or second week of January. No plant means no hot mix. You can have a crew, a purchase order and a perfectly dry yard, and still not be able to lay a square metre.
So the real productive window for school yard resurfacing in the 2026/27 break looks like this (estimate, based on typical plant and crew shutdowns):
That last one gets forgotten constantly. Teachers are usually back on site before students. You want the yard swept, line marked, fencing pulled down, bollards reinstated and a joint walk-through signed off before the first staff car pulls in, not during.
Most schools plan this forwards from "when are the holidays" and run out of runway at the procurement end. Work backwards from the day the crew needs to start.
For a 5 January 2027 start, a reasonable backwards timeline looks like this:
Scope the works, get a condition survey, decide whether you are patching, overlaying or doing a full dig out and rebuild. This decision changes the cost by a factor of three and the duration by a factor of two. Our breakdown of resurfacing versus full reconstruction covers where the line sits.
Budget confirmed, school council or council committee endorsement obtained. Do not go to market without this.
Approach the market.
Evaluate, clarify, award. Build in time for the contractor to ask questions, because the ones who don't ask questions are the ones who hit you with variations in January.
Contractor books the crew and provisionally books plant supply. Get the booking confirmed in writing with dates, not a handshake.
Pedestrian management plan, hazardous materials check, community notification drafted.
Pre-start meeting on site with the principal, the business manager, the contractor's supervisor and whoever runs vacation care.
If you are reading this in October 2026 and you have not scoped the job, a full open tender for January is tight. A quotes process under your threshold is still achievable. So is targeting the April 2027 break for a smaller scope.
Victorian government schools: construction works or services valued between $75,001 and $150,000 including GST require at least three supplier quotes uploaded into AIMS plus school council approval of the agreed quote. Above $150,000 including GST, you are into a tender process. Those are not trivial differences in elapsed time.
Councils set their own thresholds under their procurement policies, and they are usually stricter again on public tender requirements for capital works.
Confirm your current thresholds before you scope, because the easiest way to lose six weeks is to scope a $165,000 job when a staged $140,000 job would have got you on site in January. That is not gaming the rules. It is sequencing the work to match the window you actually have.
Once the gates close for the year, the people who know things stop answering emails. Get these done while staff are still on site:
Two assumptions cause most of the trouble.
The first is that the school is empty over the break. It usually isn't. Outside school hours care programs run vacation care on site through most of January, sometimes using the same toilets, the same gates and the same shade areas the crew wants to stage from. Before you sign anything, get the vacation care operator's dates, numbers and room allocation in writing, and walk the site with them. A truck reversing past a line of 40 kids in bibs is a conversation you do not want to have with a regulator.
The second is that fencing is a formality. Bunting is not a barrier. Use temporary fencing panels with shade cloth and stable feet, with a contractor gate that is physically separate from any gate a child uses. Anyone on site while students or vacation care children are present needs a valid Working with Children Check and a sign-in process. Contractor amenities and toilets stay separate from school facilities.
If works run into term, add these:
Assume it will. A wet January can cost a week, and asphalt cannot be laid onto a wet base or during rain without compromising compaction. A mat that cools too fast or sits on moisture gives you poor density, then ravelling and edge failure inside a few years. No contractor should be pressured into laying in the wet to protect your hand-back date, and any contractor who agrees to is telling you something about their workmanship.
Three things protect you here.
The yard should be safe at knock-off every single day, even if it is only compacted base with ramped edges. Agree the staging order before the first truck arrives, and sequence by operational priority: bus bay and pickup zone first, then main thoroughfares, then courts, then back-of-site areas.
Something like: if the works are not complete by the Friday before staff return, remaining stages are deferred to the April break, and the site is made safe, trafficable and handed back in that condition. Without this clause, you end up with a half-finished yard and a crew drifting in and out through Term 1 while you improvise a pedestrian route every morning.
Who absorbs the cost of a crew sitting idle for three days is worth knowing in November, not in January. Our guide to what to check in a school asphalt contract sets out the clauses that matter.
Generally no, and it is not about the crew. The asphalt plant is shut. Crack sealing, patch repairs and line marking using stock on hand are sometimes possible. Full resurfacing is not.
For laying, usually not. For use, yes. Fresh asphalt in a heatwave stays soft and scuffs from heel marks, bike stands, basketball pole bases and anything with a point load. Extend the closure, keep vehicles off longer, and do not let anyone park a trailer on it.
Foot traffic is typically fine the next day once the surface has cooled. Line marking is the catch. Many contractors prefer to wait before marking new asphalt because of residual surface oils, which means a second mobilisation. Ask at quote stage exactly when marking happens and whether it is a return visit, because a court with no lines is a court nobody books.
Check liquidated damages, then check something more useful: do you have a workable fallback for PE, lunch and pickup for two weeks? The contract gives you money. The fallback plan gives you a functioning school.
They will. Letterbox drop the surrounding streets a week out, include dates and a contact number, and confirm local noise curfew hours before agreeing to a 6am start. Councils field these calls, and a complaint can stop a shift.
That depends entirely on the base, the drainage and the traffic. A surface overlay on a failing base buys you three or four years. Our piece on why school asphalt fails early covers the drainage and subgrade issues that make the difference.
If January 2027 is already too tight for the scope you want, the April break is a genuine option for smaller works, and planning now for the 2027/28 summer gives you the one thing this job rewards most, which is lead time. If you want a second opinion on whether your scope fits the window, talk to us about a site assessment before you go to market.
GOOD Based on 11 reviews Posted on Philippa SommerTrustindex verifies that the original source of the review is Google. Mike and his team did an excellent job on my driveway. Trouble free and smooth transaction. Fast reliable and friendly crew. Very professional and l’m very pleased.Posted on Annie StuartTrustindex verifies that the original source of the review is Google. Cannot praise MR Asphalt enough! Our new driveway is just gorgeous and the whole process from start to finish has been fantastic. Mike's prompt response to our enquiry followed by next day site check by Fraser, whole-team professionalism, courtesy, great communication, amazing workmanship and Kev's meticulous brick art has given us one of the best trade experiences of all time. More than highly recommended as this team is a total stand-out. Thanks again MR and we'll be in touch re our next job soon.Posted on Bronwyn LaphamTrustindex verifies that the original source of the review is Google. I could not be happier with the work of Fraser and Kev. They were polite, friendly, extremely professional and highly skilled with great attention to detail. Excellent communication throughout the process and they delivered as promised. I can't recommend them highly enough.Posted on brendan hamiltonTrustindex verifies that the original source of the review is Google. 10/10, couldn’t recommend enough! Fraser was great to deal with, friendly and the quality of work was top notch I couldn’t have found a better company to do my driveway Thanks Fraser and the guys from Mike Rowley AsphaltPosted on Danny KahTrustindex verifies that the original source of the review is Google. Great job, communicated which days they would be in to take out the old concrete, prepare crushed rock,do the brick edging, and final asphalt. Very happy with the result !!Posted on Harry BastinTrustindex verifies that the original source of the review is Google. Top blokes got everything done on time. Dealt with Fraser, easy process. Really happy with the driveway thanks guys.Posted on Sue CarlinTrustindex verifies that the original source of the review is Google. Great job. Mike and his guys were quick and efficient. Result looks amazing. Reasonably priced and very helpful.Posted on Emily GuyTrustindex verifies that the original source of the review is Google. Excellent work, great attention to detail. My driveway is looking schmick thanks to Mick!