Construction site inspection at sunrise before asphalt paving
Asphalt Site Preparation

The Builder's Pre-Start Checklist for the Asphalt Crew: Levels, Subgrade, Services, Kerbs and Access

By Mr Asphalt October 2026 7 min read

It's 6:15 on a Tuesday morning. The paver's on the float, two trucks of asphalt are already batched and on the road, and our foreman pulls up to find the sparkie's ute parked in the middle of the car park, two pit lids sitting 40 mm low, and a base that copped rain overnight.

Nobody wants that call. Not us, not you, and definitely not the client waiting on handover.

Most asphalt jobs that go sideways don't fail on the day. They fail in the week before, when everyone assumes someone else has sorted the levels, the pits or the access. This asphalt site preparation checklist is what we wish every head contractor and site manager ran through before booking us in. It also explains, plainly, what triggers a remobilisation charge, because that's the bit nobody likes talking about until the invoice lands.

Why asphalt is less forgiving than other trades

Most trades can turn up, find a problem, and shuffle to another part of the site. We can't. Hot mix is made to order the day before or the morning of. Once it's loaded, it has a working life measured in hours, and it has to be placed and rolled hot. The Australian Standard for hot mix asphalt, AS 2150, sets minimum mix temperatures, and state road authority specs reference AS 2150 Table 12 for the minimum mix temperature, measured when the mix is first placed on the surface.

So if the site isn't ready, the material doesn't wait for you. It goes in the skip, or it goes down badly. Neither outcome is good for your job.

1. Levels: the asphalt crew is not your fix-it crew

This is the most common problem we see, and the most expensive one to ignore.

The asphalt layer is designed at a set thickness. If your base is trimmed high, we finish thin and the pavement fails early. If it's trimmed low, we fill the hole with asphalt. That sounds helpful, but run the numbers.

On a 1,000 square metre car park, every extra 10 mm of depth is 10 cubic metres of asphalt. Dense graded asphalt compacts at roughly 2.4 tonnes per cubic metre, so that's about 24 extra tonnes. Price that at your current supply rate and you'll see why "just make it up in the asphalt" is a bad plan.

Before we arrive, you need:

  • Base trimmed to design level minus the asphalt thickness, within the tolerance your spec sets
  • A survey check or level sheet you can hand our foreman on the morning
  • Falls confirmed to every pit, grate and spoon drain, especially on flat sites where there's very little room for error
  • A decision on who signs off levels if the engineer or certifier needs to see them

2. Subgrade and base: test it, roll it, keep it dry

Asphalt doesn't add strength to a weak base. It shows the weakness up, usually within the first wet season.

What needs to be done and documented:

  • Compaction test results for the base from a NATA accredited lab, if your spec requires them. Have the reports on site, not "in the post."
  • A proof roll, witnessed if your engineer requires it. Any soft spots, pumping or movement need fixing before we book, not on the morning.
  • Prime or primerseal applied and properly cured where the design calls for it
  • A clean, dry surface. No loose material, no mud tracked in by other trades, no ponding.

The question we get asked most is "can you lay on a damp base?" The honest answer: it depends on the spec, the mix and how wet. Standing water and soft, saturated base is a no. If there's been heavy rain in the 24 hours before, call us early. A rescheduled booking costs far less than a pavement that strips or ruts.

3. Services: everything under the asphalt goes in first

Once the asphalt's down, any service you forgot means a saw cut, an excavation and a patch that will never look or perform like the original mat.

Check these off:

  • Before You Dig plans current. Asset owner plans typically carry a validity of 28 or 30 days from the enquiry date, and once they expire a new enquiry must be submitted. If your project has dragged on, your plans may have lapsed without anyone noticing.
  • All pits, manholes, valve boxes and hydrant covers raised or lowered to finished asphalt level, not base level
  • Conduits and sleeves in for lighting, boom gates, CCTV, irrigation and EV chargers. EV chargers are the new classic. Clients add them after the design is locked, and nobody remembers the conduit until the car park's sealed.
  • Any services crossing under the pavement backfilled and compacted to the same standard as the base around them. Trench lines that settle show up as dips within months.

4. Kerbs and edges: cured, backfilled and agreed

Kerbs are the edge restraint for the asphalt. If they're not ready, the asphalt has nothing to compact against.

  • Kerb and channel poured and cured enough to take roller vibration. Get that from your engineer or concrete supplier in writing rather than guessing a number of days.
  • Kerbs backfilled on the back side, so they don't get pushed out when we roll
  • The finish detail at the channel lip agreed before the day. Should the asphalt sit flush or slightly proud so water runs into the channel? Sort it out at the pre-start, not with a tape measure while the mix cools.
  • Edge details for areas without kerb, such as landscaping edges, footpath junctions and existing pavement tie-ins, marked and agreed
  • Concrete splatter and form debris cleaned off the base

5. Access: can a loaded truck actually get to the paver?

This one catches out experienced site managers because the site looked fine when they walked it in a ute.

  • A clear route for loaded trucks in and out, with room to turn or reverse safely. A truck and dog needs far more room than you'd think.
  • No new concrete slabs, footpaths or crossovers in the truck path unless they're rated for the load
  • Overhead powerlines identified near any tipping area
  • Gates unlocked, keys or codes sorted, and a site contact who answers their phone at 6 am
  • Other trades, scaffolds, material stockpiles and parked vehicles cleared off the paving area
  • Traffic management plan and any council road occupancy permits approved, if trucks or the work zone touch a public road
  • Neighbours and tenants told. A shopping centre tenant blocking the entry with a delivery van can stop a pour as effectively as rain.

What actually triggers a remobilisation charge

Let's be straight about this, because it's where most disputes start.

A remobilisation charge applies when we turn up as booked and can't complete the work because the site isn't ready. It covers the crew's time, the plant that's already been floated in, and any asphalt already batched that can't be used elsewhere.

Common triggers:

Trigger 01Levels not ready or not signed off
Trigger 02Base failed proof roll or is too wet to pave
Trigger 03Pits and covers not set to finished level
Trigger 04Kerbs not poured, cured or backfilled
Trigger 05Access blocked by other trades, vehicles or locked gates
Trigger 06Permits or traffic control not in place
Trigger 07No one on site with authority to make a call

How to avoid it: two conversations that save thousands

01

The pre-start walk, 48 hours out.

Your site manager and our foreman walk the site together against this checklist. Anything not ready gets a name and a deadline.

02

The go/no-go call, the afternoon before.

Before we order the asphalt, we confirm the weather, the base condition and access. If something's slipped, we move the booking while the only cost is a phone call.

Take photos of the prepared base, pits and kerbs on the day before. If there's ever a disagreement about the site condition, photos settle it in seconds.